I-95/Butler Blvd. Ramp Improvements


Better Jacksonville Plan, BJP-2
Status Report is for August 2010

This is a rendered view of I-95/J.T. Butler Interchange project. For more information call 630-3181.

DESCRIPTION: This is a Design/Build project to add northbound and southbound I-95 entrance and exit ramps between Butler Boulevard and Bowden Road, and lengthen turn-lanes on Belfort Road to reduce traffic congestion and improve safety. Click to following links to view project renderings:

STATUS
Current Activity: CONSTRUCTION PHASE:  All work for Belfort Road has been completed.  New pavement on I-95, southbound I-95 exit ramp and northbound I-95 entrance ramp is complete.  Striping, corridor clean up and mowing has been completed.  The new lanes on Belfort Road, I-95 NB and SB, including the exit ramp onto Bowden, were opened to traffic this month.  ITS and punch-list work are ongoing. 

Funding:
Revised BJP Program allocation is $14 million.

Schedule: Construction completion anticipated in the second quarter of 2010. 

DBE/MBE: DBE participation will conform with JTA policies.

SIGNIFICANT ISSUES: Utility relocation coordination. Coordination of this improvement with planning work on US-1 to I-95 link, as a component of the JTB/I-95 ultimate configuration.

PROJECT MANAGER: Robert Opland

CONTACT:
Wendy Morrow, (904) 598-8733 or wmorrow@jtafla.com



Loading

Additional Information

All Projects
Development Projects
Mass Transit Projects
Planning Projects
Roadway Projects


Service Updates

B7-Commonwealth/Baymeadows Route Change
Effective Monday, August 23, the B7 will return to its regular, pre-detour route. Riders who have been getting on the bus on Fifth Street (between Huron Street and McDuff Avenue) should now go to First Street. The current printed schedule will still show the route as Fifth Street, however.
Stadium Shuttle Service
Stadium Shuttle Service is back. Service will begin from JTB, Orange Park, Kings Avenue and Convention Center at 5:30 p.m.  Click here for more information.
I-95/JTB Lane Closures

Lane closures are expected on both north and southbound I-95 between Bowden Rd. and JTB (from 7:30 p.m. to 5:30 a.m.) so workers can continue with thermoplastic striping and barrier wall removal. The closures start Sunday, August 29 and continue through Thursday, September 2.


Laura Street Detour
The intersection of Independent Drive and Laura Street is closed for construction. The detour will end when construction is completed. Click here for more information.

Plan Your Trip


Plan Your Trip can help you choose the best way to use transit, whether by JTA bus, The Trolley, connections to the downtown Skyway, or one of our inter-county van shuttles. Just enter your starting point and destination and then make some choices about your trip.
Learn more »